A recent relatively simple Technology and Construction Court case between a Plastering Firm and a Drylining Firm [RGB Plastering Limited v Tawe Drylining and Plastering Limited [2020] EWHC 3028 (TCC)] raised the relatively complicated issue of waiver and/or estoppel.
It is quite common for people to say that they did something or agreed to something, which they later view as being detrimental to them, because they were put under some form of economic duress at the time of doing or agreeing to the event in question. The event could be, for example, the signing up to an ‘unfavourable’ final account agreement, agreeing not to pursue further claims, or agreeing to disadvantageous contract terms. However, will the defence of economic duress hold any water?
When enforcing Adjudicator’s Decisions in Court, there are two alternative approaches, either by issuing proceedings under Civil Procedure Rules (CPR) Part 7 or under CPR Part 8.
CPR Part 7 is the conventional method of starting Court proceedings, and is the usual method of attempting to obtain summary judgment of an Adjudicator’s Decision under a modified and shortened Court procedure. A claimant may use the CPR Part 8 procedure where it seeks the Court’s decision on a question which is unlikely to involve a substantial dispute of fact. We are often asked, “What is the difference between ‘Assignment’ and ‘Novation’?”.
A recent TCC Court case (Energy Works (Hull) Limited v MW High Tech Projects UK Limited [2020] EWHC 2537 (TCC)), set out a very useful summary of the legal principles relating to ‘Assignment’ and to ‘Novation’. These legal principles are summarised below. Introduction
In June of this year (2020), the UK Supreme Court issued its judgment in the Bresco Electrical Services Limited (in Liquidation) v Michael J Lonsdale (Electrical) Limited case in which the Court concluded that Insolvent companies enjoy the right to pursue adjudications, even against respondents that have a counter-claim or cross-claim. Many commentators saw this judgment as opening the floodgates to adjudications by Insolvent companies, but a more recent Court judgment, as set out below, demonstrate that there are, or may be, certain obstacles in the way of Insolvent companies successfully enforcing Adjudicator’s Decisions in their favour. Judgment: Kew Holdings Ltd v Donald Insall Associates Ltd [2020] EWHC 1862 (TCC) dated July 2020
(Judgment link: https://www.bailii.org/ew/cases/EWHC/TCC/2020/1862.html) This judgment related to a court application by Insall seeking 3 potential court orders in respect of a £2 million damages claim Kew commenced against Insall in March 2020. The Judge, sitting in the Technology and Construction Court (“TCC”), was Mrs. Justice O'Farrell DBE. The Judge ordered Kew’s proceedings be stayed pending Kew’s payment of the sums it had been previously ordered to pay, by the same Judge, on 5 February 2019 (enforcing an adjudicator's decision in Insall’s favour). Kew were also ordered to provide £600,000 as security for costs. The Judge, however, dismissed Insall’s application to strike out Kew’s claim against it. Natural Justice in Adjudication In the case of RGB P&C Ltd v Victory House General Partner Ltd [2019] EWHC 1188 (TCC), Mrs Justice Jefford DBE, provided a useful summary of the rules of natural justice that apply to Adjudicators, as follows; From the Pilon Ltd. v Breyer Group plc [2011] EWHC 2846 (TCC) case she noted that Coulson J. held that; "22.1 The adjudicator must attempt to answer the question referred to him. The question may consist of a number of separate sub-issues. If the adjudicator has endeavored generally to address those issues in order to answer the question, then, whether right or wrong, his decision is enforceable … 22.2 If the adjudicator fails to address the question referred to him because he has taken an erroneously restrictive view of his jurisdiction (and has, for example, failed even to consider the defence to the claim or some fundamental element of it), then that may make his decision unenforceable, either on grounds of jurisdiction or natural justice …. 22.3 However, for that result to obtain, the adjudicator's failure must be deliberate. If there has simply been an inadvertent failure to consider one of a number of issues embraced by the single dispute that the adjudicator has to decide, then such failure will not ordinarily render the decision unenforceable … 22.4 It goes without saying that any such failure must also be material …. In other words the error must be shown to have had a potentially significant effect on the overall result of the adjudication … 22.5 A factor which may be relevant to the court's consideration of this topic in any given case is whether or not the claiming party has brought about the adjudicator's error by a misguided attempt to take a tactical advantage." Also, from the Jacques v Ensign Contractors Ltd. [2009] EWHC 3383 (TCC) case she noted that Akenhead J had said; “(a) The adjudicator must consider defences properly put forward by a defending party in an adjudication. (b) However, it is within an adjudicator's jurisdiction to decide what evidence is admissible and, indeed, what evidence is helpful and unhelpful in the determination of the dispute or disputes referred to that adjudicator. If, within jurisdiction, the adjudicator decided that certain evidence is inadmissible, that will rarely (if ever) amount to a breach of natural justice. The position is analogous to a court case in which the Court decides that certain evidence is either inadmissible or of such little weight and value that it can effectively be ignored: it would be difficult for a challenge to such a decision on fairness grounds to be mounted. (c) Even if the adjudicator's decision (within jurisdiction) to disregard evidence as inadmissible or of little or no weight was wrong in fact or in law, that decision is not in consequence impugnable as a breach of the rules of natural justice. (d) One will need in most and possibly all "natural justice" cases to distinguish between a failure by an adjudicator in the decision to consider and address a substantive (factual or legal) defence and an actual or apparent failure or omission to address all aspects of the evidence which go to support that defence. It is necessary to bear in mind that adjudication involves, usually the exchange of evidence and argument over a short period of time and the production of a decision within a short time span thereafter. It is simply not practicable, usually, for every aspect of the evidence to be meticulously considered, weighed up and rejected or accepted in whole or in part. Primarily, the adjudicator, needs to address the substantive issue, whether factual or legal, but does not need (as a matter of fairness) to address each and every aspect of the evidence. The adjudicator should not be considered to be in breach of the rules of natural justice if the decision does not address each aspect of the evidence adduced by the parties." The above summaries should therefore be referred to when considering how the rules of natural justice relate to Adjudicators. Peter Barnes Blue Sky ADR Ltd 2019 i This article is provided for information purposes only. It does not constitute legal advice and should not be relied on as such. No responsibility for the accuracy and/or correctness of the information and commentary set out in the article, or for any consequences of relying on it, is assumed or accepted by the writer or by Blue Sky ADR Ltd. If specific advice is required, Blue Sky ADR Ltd should be contacted direct at admin@blueskyadr.com Duty of Care for Pure Economic Loss in NegligenceThe law of negligence is founded upon the principle that a person should take reasonable care to avoid causing foreseeable injury to others (a "duty of care"). "Injury" means personal injury and injury to property.
However, the cost of rectifying defective work is considered by the Courts to be pure economic loss which, in the absence of a special relationship giving rise to a duty of care, is not recoverable in negligence. If cracks in a negligently installed (or designed) pipe lead to an explosion which causes damage to the surrounding building, then the financial consequences of the damage to the building are recoverable. However, if the cracks in the pipe are discovered and fixed by the owner, he cannot recover that cost from the guilty party in negligence. Nor can he recover his losses occasioned by, for example, shutting down his factory while the cracks are being rectified. These two losses are known as "pure economic loss". They are generally not recoverable in negligence. The reason for this is because a duty of care must be consistent with an assumption of responsibility. There is no presumed general duty to avoid causing economic loss to another: it must be shown that such a duty was actually and deliberately assumed. This general rule was established in the Murphy v Brentwood District Council [1991] AC 398 case, where it was said; “If a builder erects a structure containing a latent defect which renders it dangerous to persons or property, he will be liable in tort for injury to persons or damage to property resulting from that dangerous defect. But if the defect becomes apparent before any injury or damage has been caused, the loss sustained by the building owner is purely economic. If the defect can be repaired at economic cost, that is the measure of the loss. If the building cannot be repaired, it may have to be abandoned as unfit for occupation and therefore valueless. These economic losses are recoverable if they flow from breach of a relevant contractual duty, but, here again, in the absence of a special relationship of proximity they are not recoverable in tort”. As we all know, rights and liabilities in construction cases are usually protected by a contractual chain, and the Courts consider that a duty of care to avoid causing pure economic loss in tort is inconsistent with the contractual structure. In the case of Thomas & Anor v Taylor Wimpey Developments Ltd & Ors [2019] EWHC 1229 (TCC), the claimants, Mr & Mrs Thomas, purchased properties from Taylor Wimpey (“TW”) on 19 January 2007. A claim made by the claimants against TW for TW’s alleged breach of duty of care at common law, arose from the allegation that log retaining walls at the rear of the back gardens of the purchased properties had been inadequately built by TW and were defective. The said Thomas & Anor case was a trial to determine preliminary issues concerning the liability of TW, and one of those preliminary issues was, did TW owe the claimants a duty of care in negligence for the loss and damage that the claimants alleged? Consistent with the finding in the Murphy case referred to above, HHJ Keyser QC, held on that preliminary issue that TW did not owe the claimants a duty of care in negligence for the loss caused by the defective log retaining walls. In fact, in the case, the claimants had acknowledged this general rule, but relied on Lord Bridge’s dictum in the above noted Murphy case that; “The only qualification I would make to [the general rule] is that, if a building stands so close to the boundary of the building owner’s land that after discovery of the dangerous defect it remains a potential source of injury to persons or property on neighbouring land or on the highway, the building owner ought, in principle, to be entitled to recover in tort from the negligent builder the cost of obviating the danger, whether by repair or by demolition, so far as that cost is necessarily incurred in order to protect himself from potential liability to third parties.” However, HHJ Keyser QC, after reviewing the authorities, found that Lord Bridge’s said ‘qualification’ was unsupported by any other authorities except for a first instance decision in Morse v Barratt (Leeds) Ltd (1993); a decision that HHJ Keyser QC said had not itself been supported by any persuasive analysis. Further, HHJ Keyser QC, considered that Lord Bridge’s qualification in the Murphy case was not consistent with the present state of the law, and found that the qualification was inconsistent with the decision in the Robinson v Jones (2011) Court of Appeal case which recognised no other basis for liability for pure economic loss in tort, other than on the basis of an assumption of responsibility. The Court of Appeal found that there was also no compelling policy justification for the suggested qualification as builders responsible for defects that pose risks to personal injury would be liable either under contract or under the Defective Premises Act. Because of this, in HHJ Keyser QC’s judgment, Lord Bridge’s qualification in the Murphy case was not good law. Therefore no duty of care was owed in the particular case that he was considering. In addition, HHJ Keyser QC said that the alleged loss in the case that he was considering did not purport to have any relation to the obviating of the risk of personal injury to third parties on the land, so the particular case in question would not have fallen within the purported ‘qualification’ in any event. Through his judgment, HHJ Keyser QC made it clear that there was no strong policy justification for an exception to the general rule that no duty of care in respect of ‘pure economic loss’ arose from negligence in respect of building defects. Peter Barnes Blue Sky ADR Ltd 2019 i This article is provided for information purposes only. It does not constitute legal advice and should not be relied on as such. No responsibility for the accuracy and/or correctness of the information and commentary set out in the article, or for any consequences of relying on it, is assumed or accepted by the writer or by Blue Sky ADR Ltd. If specific advice is required, Blue Sky ADR Ltd should be contacted direct at admin@blueskyadr.com BIM in Principle and in Practice, by our Director Peter Barnes, is now in its third edition and is an indispensable guide to BIM principles and techniques, providing clear explanations of core concepts, and answering many of the common questions that are asked about BIM.
BIM in Principle and in Practice is essential reading for civil engineers who require a firm grasp of how BIM is used and the benefits it can provide, and is also ideal reading for students on courses covering BIM techniques - see flyer below. In June of this year (2018) the sixth Technology and Construction Court judgment in respect of an on-going dispute between Imperial Chemical Industries Limited ("ICI") and Merit Merrell Technology Limited ("MMT") was published. Paragraph 428 of that very long judgment (the very last paragraph of the judgment) makes interesting reading. That paragraph said ‘… This litigation also stands as something of an advertisement for adjudication. The amount of the MMT account for the works, finally determined (in court) after the expenditure of legal and experts’ fees measured in millions of pounds, is barely 1% more than the amount awarded to MMT in the adjudications. The issue of who repudiated the contract was resolved in the litigation in the liability judgment with the same result as that given by the Adjudicator in the 3rd adjudication.’ It is clear from the above, that it would have been much quicker and much less expensive if ICI and MMT had simply relied upon the adjudication process rather than on the litigation process; and from our experience that is the position in respect of most claims that we see. Peter Barnes Blue Sky ADR August 2018 |